Simulation of trajectory correction in early commissioning of the Advanced Light Source upgrade
Published Web Location
http://doi.org/10.18429/JACoW-IPAC2018-THPMF078No data is associated with this publication.
Abstract
The ALS upgrade into a diffraction-limited soft x-rays light source requires a small emittance, which is achieved by much stronger focusing than in the present ALS. Very strong focusing elements and a relatively small vacuum chamber make the required rapid commissioning a significant challenge. This paper will describe the progress towards a start-to-end simulation of the machine commissioning and present first simulation results.